Goodrich athletic facilities taking shape

Posted

The Goodrich ISD financial audit produced high marks, and positive facility construction reports were given at the regular monthly meeting for November Thursday in the administration building.

Goodrich received an unmodified financial audit, which is the highest opinion possible. It states that all numbers are presented fairly.

Schoolwide, there was an increase in net position of just over $470,000. There is over 100% of the fund balance in cash, considered highly liquidable. A majority of it is in investments, which are earning well this year. Total revenues increased just over $500,000 and expenditures went up just under $600,000. Most of that was a payroll increase.

Goodrich also had $742,000 of construction work, but still increased the general fund balance just under $75,000 for the year. The ending fund balance of $6.1 million compared to total annual expenditures accounts for nearly 86% of annual expenditures in the fund balance, considered very healthy.

The district could operate almost 90% of the next year without receiving any more funds from the state. Goodrich expected to spend about $400,000 and ended up in the positive of about $75,000.

In maintenance and operation, the athletic facilities are coming together quickly, according to the superintendent.

“They finally got the building in. It was dropped on Wednesday at about noon,” Goodrich Superintendent Daniel Barton said. “They got it unloaded. The erectors, the same company that built the building, are the same guys that are erecting it. They showed up, unloaded and started right then. They’ve worked on it a day and a half. The frame’s already pretty much set.”

The facility is expected to be completed in December.

The track is also underway, where rubber is being placed. It was expected to be near completion, ready for striping after the weekend. The pole vault plant box where the pole is placed during competition is rusted and will need changing.

December is also the best estimate for the track facility to be complete. After a hard rain, the new drainage held up well. There was one puddle on the asphalt, which has already been addressed.

The district’s special education bus is going to the shop this week for work on the back two air conditioners.

Also scheduled for the week is a water line repair that burst underground.

“There’s a large majority of it that’s associated with high pressure, high water pressure,” Barton said. “So we’re putting in a new regulator on Monday morning. We’ll put in on our main line coming into the middle school and high school. We rolled that in as part of the athletic facilities, rather than putting a regulator on the athletic facilities, which we did in the ag building. That’ll go in Monday, and then the guys are going to try to dig it up. We’ve got three underground leaks back there right now that it just seeps up. So, we’ve rented a mini excavator.”

The main breaker for the cafeteria continues to throw for no reason the school can find. “It’s random at best,” Barton said. “The only thing that doesn’t seem random is it seems to happen when we’re not here. It’s very strange. It’s on the weekend, and then it kicks on our generator out there that runs on natural gas.”

The district had two electric companies out looking at the breaker.

A retention bonus that is given out in December of $500 was approved. Goodrich has given this out for multiple years now for teachers and staff who return in the second semester. It is distributed when school is out for Christmas break.